Bennet Shores East - Phase 1
|
Date |
| Abatement/Demo |
16 Jun 08 |
| Site Prep |
17 July 08 |
| Construction |
16 Sept.08 |
| Begin Turnover of Units (50) |
Summer 09 |
Bennet Shores East - Phase 2
|
Date |
| Abatement/Demo |
15 Dec.09 |
| Site Prep |
16 Feb.10 |
| Construction |
16 April 10 |
| Begin Turnover of Units (49) |
Spring 11 |
Bennet Shores East - Phase 3
|
Date |
| Abatement/Demo |
18 July 11 |
| Site Prep |
14 Sept.11 |
| Construction |
12 Oct. 11 |
| Begin Turnover of Units (51) |
Summer 12 |
Bennet Shores West
|
Date |
| Abatement/Demo |
26 Dec.11 |
| Community Center |
Spring 12 |
Ribault Bay - Phase 1
|
Date |
| Abatement/Demo |
15 Aug 08 |
| Site Prep |
15 Sep 08 |
| Construction |
18 Sept.08 |
| Begin Turnover of Units (44) |
Summer 09 |
Ribault Bay - Phase 2
|
Date |
| Abatement/Demo |
29 May 09 |
| Site Prep |
30 July 09 |
| Construction |
30 Sept.09 |
| Begin Turnover of Units (50) |
Spring 10 |
Ribault Bay - Phase 3
|
Date |
| Abatement/Demo |
11 June 10 |
| Site Prep |
12 Aug.10 |
| Construction |
12 Nov.10 |
| Begin Turnover of Units (64) |
Fall.11 |